Australia’s largest renewable energy project, Snowy Hydro 2.0, has been hit by another delay pushing out its timeline by another one to two years.
Dennis Barnes, the CEO and managing director of Snowy Hydro 2.0 has provided an update on the progress of the multi-billion dollar project, whose completion date has been extended several times.
The CEO cited three problems for the latest round of delays: issues with tunnelling machines, the availability of materials and labour and the impacts of the pandemic.
“A combination of factors has meant that it’s pretty clear that the schedule will go out by between one and two years,” he told ABC Radio….
-
Recent Posts
-
Archives
- May 2025
- April 2025
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- September 2013
- July 2013
- March 2013
- January 2013
- December 2012
- November 2012
- December 1
-
Meta