Some UK solar farm developers have been told that they face a 15–20 year wait to connect to local electricity grids, which the energy regulator claims is a “major problem” as the government wants to decarbonise its power system by 2035.
Blockages in the network mean that some solar farm developers will only be connected to local electricity grids by the 2030s, with the government recognising “the challenge of connection delays.”
In May, the trade organisation Solar Energy UK said that waiting times for large solar projects’ connection to the electricity grid, both on roofs and ground, “can often stretch well into the 2030s.”…
-
Recent Posts
-
Archives
- May 2025
- April 2025
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- September 2013
- July 2013
- March 2013
- January 2013
- December 2012
- November 2012
- December 1
-
Meta