Commentary
When the transit gravy train comes to town you won’t be on it. But somebody will, so look out.
Here in Ottawa, we gaze in weary resignation at headlines like “City says expansion of western LRT delayed up to one year” as our much-vaunted light rail crashes expensively into yet another bizarre obstacle. Sure, it’s a big project. But it’s not like subways are a new thing, so why didn’t they see it coming?
It’s especially aggravating to read, “The western extension could be the most technically delicate part of the $4.6-billion, three-direction Stage 2 project” because the “O-Train” has already encountered technical delicacies like wheels that were “not perfectly round” and cars tested with the wrong kind of snow. So we could be in a heap of trouble when they get to really fiddly stuff like doors not opening or trains derailing or stations smelling of sewage….
-
Recent Posts
-
Archives
- May 2025
- April 2025
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- September 2013
- July 2013
- March 2013
- January 2013
- December 2012
- November 2012
- December 1
-
Meta