Transport Secretary Mark Harper has announced that “inflationary pressures” will cause delays to the construction of key parts of the high-speed railway HS2.
In a written ministerial statement, Harper said the Birmingham to Crewe line will be delayed by two years and the final stretch from Old Oak Common in west London to Euston in central London will not be ready until some time in the 2040s.
The priority will be the section from Old Oak Common to Birmingham’s Curzon Street station, but plans for the next part—from England’s second city north to the key railway junction town of Crewe—has been delayed….
-
Recent Posts
-
Archives
- May 2025
- April 2025
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- September 2013
- July 2013
- March 2013
- January 2013
- December 2012
- November 2012
- December 1
-
Meta