The modernization of Parliament’s Centre Block is within budget so far, but the federal government needs to do a better job at making up their minds before major construction begins, the federal auditor general says in a new report.
Karen Hogan warns in a report released Monday that if decision-making remains fragmented, it could lead to construction delays—and more costs for taxpayers.
The rehabilitation of Centre Block already comes with a price tag of up to $5 billion, and is set to be completed by 2031.
“Given the size and complexity of this undertaking, a streamlined decision-making process will be required to continue effectively managing the costs and timelines of the rehabilitation program, as construction work accelerates between now and the planned completion date,” reads the report, which covers the period from January 2010 until July 2022….
-
Recent Posts
-
Archives
- May 2025
- April 2025
- July 2023
- June 2023
- May 2023
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- May 2021
- April 2021
- March 2021
- February 2021
- January 2021
- December 2020
- September 2013
- July 2013
- March 2013
- January 2013
- December 2012
- November 2012
- December 1
-
Meta